Projects Statistics

Double Rear Extension & Internal Modifications 


Location: Rayleigh, Essex. 

Quote Price: £121,000.00 

Final Price: £118,000.00 

Estimated Time Scale: 16 Weeks 

Actual Time Scale: 16 Weeks 

Project Manager Notes: “This was a straightforward but interesting project we managed to get through our schedule in a timely manner with constraints that were not in our control. A great project”. 

Double Rear extension, Loft conversion & Outbuilding


Location: Orpington, Kent.  

Quote Price: £290,000.00  

Final Price: £320,000.00 

Estimated Time Scale: 20 weeks  

Actual Time Scale: 22 weeks

Project Manager Notes: “A project that is quite typical for me, but the challenges came with the client’s intricate bespoke finishing requirements, we certainly enjoyed completing this and were really happy with the client’s reaction at the reveal.” 

Double-storey rear and wraparound extension, internal mods & landscaping 

Location: Gravesend, Kent.  

Quote Price: £327,000.00   

Final Price: £310,000.00 

Estimated Time Scale: 32 weeks  

Actual Time Scale: 37 weeks

Project Manager Notes:  “Having been delayed by changing building control regulations, we finished a few weeks later than expected but, it allowed us to finesse the wraparound and source some great internal mods”. 

Rear extension – Kitchen Renovation 

Location:  Park Royal 

Quote Price: £65,000.00 

Final Price: £65,000.00   

Estimated Time Scale: 13 weeks  

Actual Time Scale: 13 weeks

Project Manager Notes:  “Very quick job, and managed to get the client trade discount on the kitchen which really helped keep costs controlled for the client”. 

Loft Conversion & Double Ensuite

Location:   Slough 

Quote Price: £55,000.00 

Final Price: £55,000.00 

Estimated Time Scale: 12 weeks

Actual Time Scale: 18 weeks

Project Manager Notes:  “An exciting project for a newly married couple looking to turn their attic into the ultimate bedroom.  Price increased because of dual aspect requirement namely but in good taste, with balcony at the back”. 

Demolition & New Build of 4 Flats with rear patio and driveway

Location:  Tunbridge Wells,

Quote Price: £550,000.00 

Final Price: £515,000.00

Estimated Time Scale: 32 weeks

Actual Time Scale: 37 weeks

Project Manager Notes:  “A great demolition phase set us in good stead time-wise, we had a good relationship with the council Building Control and guidance made the process a lot quicker especially for a new builder.  We managed to achieve the 5% VAT exemption due to the nature of the project”. 

Demolition & New Build of 4 Flats with rear patio

Location: Bromley

Quote Price: £525,000.00

Final Price: £497,000.00

Estimated Time Scale: 32 weeks

Actual Time Scale: 35 weeks

Project Manager Notes:  “Certainly great to be repeating a project for a client, and managed to achieve the 5% VAT exemption due to the nature of the project again”. 

Commercial Factory Fit-Out

Location: Harrow

Quote Price: £300,000.00

Final Price: £311,000.00

Estimated Time Scale: 12 weeks

Actual Time Scale: 12 weeks

Project Manager Notes:  “A wide scope commercial project, increasing the floor space in a bid to provide for the quick company expansion. A consultative process and many changes to scope were requested through and through however, nothing we were not able to deliver. Certainly a client we would love to work with again”. 

Double Rear Extension, New Roof & Internal Works

Location: Southend

Quote Price: £351,000.00

Final Price: £375,000.00

Estimated Time Scale: 18 weeks

Actual Time Scale: 18 weeks

Project Manager Notes:  “The loft extension and outbuilding brought space to the property in abundance.  Copious amounts of internal renovations, as well as the addition of a new kitchen, increased the price, very happy with the result”. 

single storey rear extension and Complex internal modification

Location: Benfleet

Quote Price: £320,000.00

Final Price: £335,000.00

Estimated Time Scale: 20 weeks

Actual Time Scale: 20 weeks

Project Manager Notes:  “As one of our more regular builds and as we had just completed a job prior, we were able to mobilize the teams very quickly, keeping time scales and quality in check”. 